[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388842,172,1,"单选题","根据以下某项目的网络图，在最佳的人力资源利用情况下，限定在最短时间内完成项目，则项目的人力资源要求至少为 （ ） 人。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","9",false,{"key":16,"text":17,"correct":14},"B","8",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","6","项目最佳配置人力资源的技术是资源平衡技术。要保证项目在最短时间内完成，活动B的4人工作7天是要确保的。活动A和活动C由于时间相加也是7天，所以可如下安排：3人完成活动C后有两人接着进行活动A。所以，该项目的人力资源要求至少为7人。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]