[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388837":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388837,172,1,"单选题","某项任务由子任务Ⅰ（计划编制和批准）和子任务Ⅱ（计划实施）组成。项目经理认为子任务Ⅰ的乐观历时为3天，最可能为4天，悲观历时为8天；子任务Ⅱ的乐观历时为5天，最可能6为天，悲观历时为10天。根据估算，该任务估算历时为 （ ） 天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":18},"B","11",true,{"key":20,"text":21,"correct":14},"C","12",{"key":23,"text":24,"correct":14},"D","13","用三点估算法，估算活动平均时间为（乐观历时 + 4 ? 最可能历时 + 悲观历时）\u002F6计算可得，子任务Ⅰ的平均时间为4.5天，子任务Ⅱ的平均时间为6.5天。因此该任务估算历时为“4.5天 + 6.5天 = 11天”。故选B。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]