[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388835":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388835,172,1,"单选题","进度控制是避免工期拖延的一种方法。进度控制中的纠正行为通常加速某些活动以确保这些活动能够及时完成。为了重新编制和执行进度表，纠正行为通常要求_____。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","做大家都不喜欢的决策",false,{"key":16,"text":17,"correct":14},"B","及时调整基线",{"key":19,"text":20,"correct":21},"C","进行原因分析",true,{"key":23,"text":24,"correct":14},"D","资源平衡","一般情况下，进度控制的步骤如下：分析实际进度与计划进度；如果进度落后，找出落后的原因；针对进度落后原因，制订并选择纠正措施。所以，正确选项是C。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]