[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388825":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388825,172,1,"单选题","某项目各项工作的先后顺序及工作时间如下表所示，该项目的总工期为 （ ） 天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","31",false,{"key":16,"text":17,"correct":18},"B","32",true,{"key":20,"text":21,"correct":14},"C","33",{"key":23,"text":24,"correct":14},"D","34","根据表格，可画出该项目的进度网络图，找出关键路径为：A->D->F->G->I，根据关键路径上各个活动的持续时间，计算出总工期为：5+6+13+6+2=32。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]