[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388824":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388824,172,1,"单选题","某企业拟建设一个面向生产管理的信息系统，以提高企业的生产管理水平。该项目的建设期为2年，运营期为7年。在某工程咨询单位编制的项目可行性研究方案中，项目各年预计净现金流量（NC F）、折现系数以及计算出的折现净现金流如下表所示（贴现率为10%）。建设单位要求监理对方案投资的可行性提出监理意见。 根据上表给出的数据，计算项目的净现值为（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","410.46",false,{"key":16,"text":17,"correct":14},"B","411.46",{"key":19,"text":20,"correct":21},"C","411.52",true,{"key":23,"text":24,"correct":14},"D","411.62","项目净现值=186.36+169.42+154.03+140.03+127.29+317.17-（345.46+330.56+6.76）=411.52万元",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]