[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388822":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388822,172,1,"单选题","某工程网络计划图如下所示，其各工作的持续时间压缩费率、正常持续时间和最短时间在箭线上下标出，该工程要求26d内完成，试进行网络计划调整，计算后该项目的赶工费用为（）元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1200",false,{"key":16,"text":17,"correct":14},"B","1310",{"key":19,"text":20,"correct":14},"C","1320",{"key":22,"text":23,"correct":24},"D","1350",true,"原网络计划计算工期为34d，需压缩8d。 第一次计算：将赶工费率最低的关键工作⑤→⑥缩短2d，④→⑤缩短2d，②→④缩短2d，工期共缩短6d。关键线路变为两条：①→②→④→⑤→⑥，①→③→⑥。总工期为28d。赶工费用为：150*2+120*2+90*2=720元第二次计算：将关键工作②→④缩短1d，①→②缩短1d，同时③→⑥缩短2d，工期共缩短2d。关键线路变为两条：①→②→④→⑤→⑥，①→③→⑥。总工期为26d。赶工费用为：200*1+150*1+140*2=630元总赶工费用为720+630=1350元调整后的网络计划计算工期为26d。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]