[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388821":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388821,172,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，边上的数字表示活动的持续时间（天），则完成该项目的最少时间为（请作答此空）天。活动BD和HK最早可以从第（ ）天开始。（活动A B、AE和AC最早从第1天开始）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","17",false,{"key":16,"text":17,"correct":14},"B","18",{"key":19,"text":20,"correct":14},"C","19",{"key":22,"text":23,"correct":24},"D","20",true,"项目的工期是从开始到结束持续时间最长的工作。题目中持续时间最长的是ABDIJL，需要时间20天。BD活动在AB活动结束之后便可以开始，所以最早开始时间为4。HK活动需要在AEGH与ACFH两条路径上的活动均完成之后，才能开始，所以最早开始时间为11。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]