[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388818":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388818,172,1,"单选题","下表给出了某信息系统建设项目的所有活动截止到2018年6月1日的成本绩效数据，项目完工预算BAC为30000元。 该项目的成本和进度执行情况（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本超支与进度滞后",false,{"key":16,"text":17,"correct":14},"B","成本超支与进度超前",{"key":19,"text":20,"correct":21},"C","成本节约与进度滞后",true,{"key":23,"text":24,"correct":14},"D","成本节约与进度超前","PV=1000+1500+3500+800+2300+4500+2200+2500+4200+3000=25500元EV=1000+1500+3500+800+2300+4500*0.8+2200+2500*0.6+4200*0.5+3000*0.5=20000元AC=1000+1600+3000+1000+2000+4000+2000+1500+2000+1600=19700元CPI=EV\u002FAC=20000\u002F19700=1.02SPI=EV\u002FPV=20000\u002F25500=0.78",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]