[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388817":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388817,172,1,"单选题","某信息系统项目包括如下十个活动，各活动的历时、活动逻辑关系如下表所示： 该项目的总工期是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","19",false,{"key":16,"text":17,"correct":14},"B","20",{"key":19,"text":20,"correct":21},"C","21",true,{"key":23,"text":24,"correct":14},"D","22","关键路线：ADCEIJ，总工期：21天E在关键路线上，它的总时差、自由时差均是0天；G的总时差、自由时差均是1天。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]