[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388815":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388815,172,1,"单选题","某项目由P1、P2、P3、P4、P5五个活动组成，五个活动全部完成之后项目才能够完成，每个活动都需要用到R1、R2、R3三种互斥资源，三种资源都必须达到活动的资源需求量，活动才能开始。已分配资源只有在完成本活动后才能被其他活动所用。目前项目经理能够调配的资源有限，R1、R2、R3的可用资源数分别为9、8、5。活动对资源的需求量、已分配资源数和各活动历时如下表所示(假设各活动之间没有依赖关系): 基于以上案例，请计算项目的完工时间为（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":14},"C","6",{"key":22,"text":23,"correct":24},"D","7",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]