[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388811":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":28},388811,172,1,"单选题","一个估算员判定一个任务乐观估计需5天完成，悲观估计16天，但通常会花8天，采用三点估算得到的工期是（ ）天。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","8.0",false,{"key":16,"text":17,"correct":18},"B","8.8",true,{"key":20,"text":21,"correct":14},"C","9.1",{"key":23,"text":24,"correct":14},"D","9.7",{"key":26,"text":27,"correct":14},"E","10.5","代入计算公式： （5+4×8+16）\u002F6=8.8 相关知识点见薛大龙博士、孙烈阳老师“计算专题”授课视频",{"id":6,"name":30,"category":31,"favorite":32},"(高级)信息系统项目管理师","职业资格",0]