[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388810":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388810,172,1,"单选题","一个活动，最乐观估算要6天：最可能估算要21天；最悲观估算要36天；那么，该活动在16天到26天的时间完成的几率为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","54%",false,{"key":16,"text":17,"correct":18},"B","68%",true,{"key":20,"text":21,"correct":14},"C","95%",{"key":23,"text":24,"correct":14},"D","99.73%","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]