[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388809":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388809,172,1,"单选题","某软件的工作量是20000行，由4人组成的开发小组开发，每个程序员的生成效率是5000行／人月，每队程序员的沟通成本是250行／人月，则该软件需要开发（ ）月。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","1.04",{"key":19,"text":20,"correct":14},"C","1.05",{"key":22,"text":23,"correct":24},"D","1.08",true,"沟通路径[（4-1）＊40]\u002F2=6 总沟通成本6＊250=1500 每人沟通效率5000-1500\u002F4=4625 完工时间=20000\u002F4625*4=1.8",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]