[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388807":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388807,172,1,"单选题","某项目计划08年12月5日开始进入首批交付的产品测试工作，估算工作量为8（人）×10（天），误差为2天，则以下（）理解正确（天指工作日）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","表示活动至少需要8人天，最多不超过10人天",false,{"key":16,"text":17,"correct":18},"B","表示活动至少需要8天，最多不超过12天",true,{"key":20,"text":21,"correct":14},"C","表示活动至少需要64人天，最多不超过112人天",{"key":23,"text":24,"correct":14},"D","表示活动至少需要64天，最多不超过112天","该产品测试工作需要的工作量为：8人工作10天，为80人天。产品测试工作的历时为10±2天，因此该产品测试工作的历时在8～12天之内。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]