[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388806":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388806,172,1,"单选题","多个项目需要同一资源，否则不便能实施。为使延误的项目数最少，应将该资源优先分配给 （ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总时差最短的项目",true,{"key":16,"text":17,"correct":18},"B","历时最短的项目",false,{"key":20,"text":21,"correct":18},"C","计划开始最早的项目",{"key":23,"text":24,"correct":18},"D","计划结束最晚的项目","缩短项目的工期，首先应当在关键路径上缩短，如果不在关键路径，则应当在总时差最短的项目上分配资源。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]