[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388805":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388805,172,1,"单选题","项目经理要对WBS中标号为2.2.3号的工作包设定一个控制点，以便对其成本、进度、质量进行监控，再次比较适合设定一个 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","WBS字典",false,{"key":16,"text":17,"correct":18},"B","控制账户",true,{"key":20,"text":21,"correct":14},"C","账户编码",{"key":23,"text":24,"correct":14},"D","活动基线","WBS字典就是一种管理的规范化、标准化的工具，用于描述和定义WBS元素中的工作的文档。控制账户是在WBS中提出的概念，是在规划包以下，工作包以上，便于管理监控设置的控制点。账目编码是用于唯一确定项目工作分解结构每一个单元的编码系统。成本和资源被分配到这一编码结构中。活动基线是开发软件文档或源码活动的一个稳定版本，是进一步开发的基础。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]