[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388799":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388799,172,1,"单选题","公司上个月取消了由张工管理的视频游戏项目的需求定义文件和范围说明。现在公司要求将该项目成果变成可在个人电视及计算机上玩的交互游戏。这至少 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","需要修改项目既定的由WBS定义的范围",true,{"key":16,"text":17,"correct":18},"B","导致所有项目基准的改变",false,{"key":20,"text":21,"correct":18},"C","导致成本、时间、质量和其他目标的调整",{"key":23,"text":24,"correct":18},"D","会得到一个教训","项目定义过程是详细描述项目和产品的过程，并把结果写进详细的项目范围说明书中，作为将来项目决策的基准。范围变更是整体范围变更控制的一个结果，据此，张工至少需要修改项目既定的由WBS定义的范围，尽管一项范围变更会要求其化项目基线和目标的相应调整同步，但是这种评估应该就不同的情况而论。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]