[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388794":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388794,172,1,"单选题","创建WBS的输入包括 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目管理计划",false,{"key":16,"text":17,"correct":14},"B","成本估算",{"key":19,"text":20,"correct":14},"C","WBS模板",{"key":22,"text":23,"correct":24},"D","项目范围管理计划",true,"创建WBS过程的输入包括组织过程资产、项目范围说明书、项目范围管理计划和已批准的变更请求。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]