[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388793":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388793,172,1,"单选题","某公司在项目执行过程中，对项目需求进行收集分析，并形成正式的项目文档，并由客户签字确认，但在交货时发现，实际产品与客户的要求大相径庭，客户拒绝付款。经调查研究发现，需求来源和低层需求实现不完全匹配，这可能是在 （ ） 方面出了问题。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","制定需求管理计划",false,{"key":16,"text":17,"correct":18},"B","维护对需求的双向跟踪性",true,{"key":20,"text":21,"correct":14},"C","求得对需求的承诺",{"key":23,"text":24,"correct":14},"D","管理需求变更","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]