[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388792":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388792,172,1,"单选题","某信息系统项目在项目预测与评估的过程描述如下：①聘请多领域专家采取背对背的方式进行；②借助问卷获取专家的评估结论；③汇总问卷结果并在专家间传阅；④专家调整各自评估结论；⑤通过多轮征询获得专家对项目评估的一致见解。那么该项目的评估采用的方法是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","相关关系法",false,{"key":16,"text":17,"correct":14},"B","头脑风暴法",{"key":19,"text":20,"correct":21},"C","德尔菲法",true,{"key":23,"text":24,"correct":14},"D","SWOT方法","相关关系法特点：软件项目和效益之间有明显的相关关系。头脑风暴法特点：要集中有关人员召开专题会议，主持者说明问题和会议的规则，尽力创造融洽轻松的会议气氛。主持者一般不发表意见，由相关人员“自由”提出尽可能多的方案。德尔菲法的特点：聘请多领域专家采取背对背的方式进行；借助问卷获取专家的评估结论；汇总问卷结果并在专家间传阅；专家调整各自评估结论；通过多轮征询获得专家对项目评估的一致见解。SWOT方法的特点：S—内部优势；W—内部劣势；O—外部机会；T—外部威胁，用于战略分析。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]