[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388791":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388791,172,1,"单选题","某项目经理在对项目历时进行估算时，认为正常情况下完成项目需要42天，同时也分析了影响项目工期的因素，认为最快可以在35天内完成工作，而在最不利的条件下则需要55天完成任务。采用三点估算得到的工期是 ___天",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","42",false,{"key":16,"text":17,"correct":18},"B","43",true,{"key":20,"text":21,"correct":14},"C","44",{"key":23,"text":24,"correct":14},"D","45","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]