[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388786,172,1,"单选题","在项目实施期间的某次周例会上，项目经理向大家通报了项目目前的进度。根据以下表格特征，目前的进度 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","提前计划7%",false,{"key":16,"text":17,"correct":14},"B","落后计划15%",{"key":19,"text":20,"correct":21},"C","落后计划7%",true,{"key":23,"text":24,"correct":14},"D","提前计划15%","在目前的监控点，该项目的挣值EV、PV及SPI如下： EV=20000X90%+50000X90%+30000X100% =93000 PV=20000+50000+30000 =100000 SPI=EV\u002FPV =93000\u002F100000 =93% 落后于进度计划：1-93%=7%",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]