[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388785":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388785,172,1,"单选题","在项目某阶段的实施过程中，A活动需要2天2人完成，B活动需要2天2人完成，C活动需要5天4人完成，D活动需要3天2人完成，E活动需要1天1人完成，该阶段的时标网络图如下。该项目组共有8人，且负责 A、E活动的人因另有安排，无法帮助其他人完成相应工作，且项目整个工期刻不容缓。以下 ______安排是恰当的，能够使实施任务顺利完成",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","A. B.活动提前两天开始",false,{"key":16,"text":17,"correct":14},"B","B.活动推迟两天开始",{"key":19,"text":20,"correct":14},"C","活动提前两天开始",{"key":22,"text":23,"correct":24},"D","活动推迟两天开始",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]