[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388781":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388781,172,1,"单选题","某工程包括 A、 B、 C、 D、 E、 F、 G、H八个作业，各个作业的紧前作业、所需时间和所需人数如下表所示（假设每个人均能承担各个作业）：该工程的工期应为 （ ） 周",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","8",true,{"key":16,"text":17,"correct":18},"B","9",false,{"key":20,"text":21,"correct":18},"C","10",{"key":23,"text":24,"correct":18},"D","11","题干给定条件画出双代号网络圈，再加时标，并对该网络图进行调整，形成时标网络图 从上图可以直观地看出，关键路径为ACEGH，工程工期为2+1+2+2+1=8。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]