[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388780":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388780,172,1,"单选题","A公司的某项目即将开始，项目经理估计该项目10天即可完成，如果出现问题耽搁了也不会超过20天完成，最快6天即可完成。根据项目历时估计中的三点估算法，你认为该项目历时的估算标准差为 ：（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2.1天",false,{"key":16,"text":17,"correct":14},"B","2.2天",{"key":19,"text":20,"correct":21},"C","2.3天",true,{"key":23,"text":24,"correct":14},"D","2.4天","标准差是（20-6）\u002F6=2.3",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]