[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388779":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388779,172,1,"单选题","进度风险导致的损失不包括（ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","货币的时间价值",false,{"key":16,"text":17,"correct":14},"B","延期投入导致的损失",{"key":19,"text":20,"correct":21},"C","预算不准导致的成本超支",true,{"key":23,"text":24,"correct":14},"D","进度延误引发的第三方损失","预算不准确不属于进度风险，是属于成本管理内容。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]