[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388778":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388778,172,1,"单选题","某项目由ABCDE五个活动构成，完成各活动工作所需要的最可能时间Tm、最乐观时间To、最悲观时间Tp见下表： 各活动之间的信赖关系如下： 则该项目工期的估算结果约为 （ ） 天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","22",false,{"key":16,"text":17,"correct":14},"B","23",{"key":19,"text":20,"correct":21},"C","24",true,{"key":23,"text":24,"correct":14},"D","25","先找出关键路径：关键路径是：1-3-5-6，求B，D，E 3个活动的最可能时间之和，B是（5×4+2+10）\u002F6，D是（7×4+3+15）\u002F6，E是（10×4+6+20）\u002F6，3者相加等于24。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]