[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388777":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388777,172,1,"单选题","完成某信息系统集成项目中的一个最基本的工作单元A所需的时间，乐观的估计需8天，悲观的估计需38天，最可能的估计需20天，按照PERT方法进行估算，项目的工期应该为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":18},"B","21",true,{"key":20,"text":21,"correct":14},"C","22",{"key":23,"text":24,"correct":14},"D","23","用PERT法， 估算活动的工期=（乐观估算+4*最可能估算+悲观估算）\u002F6=21",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]