[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388769,172,1,"单选题","活动排序的工具和技术有多种，工具和技术的选取由若干因素决定。如果项目经理决定在进度计划编制中使用标准化的项目进度网络图，这可能因为 （ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","该项目非常独特，在不同的阶段需要专门的网络图",false,{"key":16,"text":17,"correct":14},"B","在现有网络上具有可以获取的资源管理软件",{"key":19,"text":20,"correct":21},"C","在项目中包含几个相同或几乎相同的可交付成果",true,{"key":23,"text":24,"correct":14},"D","项目中存在多条关键路径","由题干中的“标准化”，可知这是“复用”、“模版”的思想。既然可以复用，就说明是“在项目中包含几个相同或几乎相同的可交付成果”。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]