[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388765":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388765,172,1,"单选题","某待开发的信息系统工作分解结构图如下图，其中标有“（1）”的方框应该填入的内容是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","同行评审",false,{"key":16,"text":17,"correct":14},"B","计划评审",{"key":19,"text":20,"correct":21},"C","项目计划制定",true,{"key":23,"text":24,"correct":14},"D","集成方案制定","本题考查的是WBS的相关知识，根据分解原则及软件工程基础知识。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]