[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388757":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388757,172,1,"单选题","（ ） 不是WBS的正确分解方法或结构。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","把主要的项目可交付物和子项目作为第一层",false,{"key":16,"text":17,"correct":18},"B","在同一WBS层上采用不同的分解方法",true,{"key":20,"text":21,"correct":14},"C","在不同WBS层上可采用不同的分解方法",{"key":23,"text":24,"correct":14},"D","把项目生命期作为第一层，项目交付物作为第二层","分解WBS结构的方法有以下几种：（1） 把项目生命期作为第一层，项目交付物作为第二层。（2） 把项目重要的可交付物作为分解的第一层。（3） 在不同WBS层上可采用不同的分解方法。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]