[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388756":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388756,172,1,"单选题","在系统建设后期，建设方考虑到系统运维管理问题，希望增加8课时的IT服务管理方面的知识培训，承建方依此要求进行了范围变更。在对范围变更进行验证时，验证准则是（ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","学员签到表",false,{"key":16,"text":17,"correct":14},"B","安排一次考试，以测验分数",{"key":19,"text":20,"correct":21},"C","新批准的培训工作方案",true,{"key":23,"text":24,"correct":14},"D","培训范围变更请求","题干中项目范围发生了变更，承建单位依据建设方的要求进行了范围变更管理。其步骤应包括提交范围变更申请、对范围变更影响进行分析并交CCB审批、执行变更、对范围变更进行验证、干系人沟通并确认、归档。对培训效果进行验证的准则应该是批准后的培训方法与策略工作方案，故正确选项是C。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]