[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388752":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388752,172,1,"单选题","典型的信息系统项目开发的过程中， （ ）阶段拟定了系统的目标、范围和要求，而系统各模块的算法一般在 （请作答此空） 阶段确定。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","概要设计",false,{"key":16,"text":17,"correct":14},"B","需求分析",{"key":19,"text":20,"correct":21},"C","详细设计",true,{"key":23,"text":24,"correct":14},"D","架构设计","需求分析拟定了系统的目标、范围和要求；而系统各模块的算法一般在详细设计阶段确定。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]