[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388751":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388751,172,1,"单选题","（ ） 不属于范围变更控制的工作。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","确定影响导致范围变更的因素，并尽量使这些因素向有利的方面发展",false,{"key":16,"text":17,"correct":14},"B","判断范围变更是否已经发生",{"key":19,"text":20,"correct":14},"C","管理范围变更，确保所有被请求变更按照项目整体变更控制过程处理",{"key":22,"text":23,"correct":24},"D","确定范围正式被接受的标准和要素",true,"范围变更控制的工作有：（1）确定影响导致范围变更的因素，并尽量使这些因素向有利的方面发展。（2）判断范围变更是否已经发生。（3）范围变更发生时管理实际的变更，确保所有被请求的变更按照项目整体变更控制过程处理。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]