[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388746":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388746,172,1,"单选题","关于活动历时估算的说法不正确的是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","活动历时估算不是进行活动排序时首要考虑的问题",false,{"key":16,"text":17,"correct":18},"B","活动历时估算的准确性不依赖于项目团队成员对项目的熟悉程度",true,{"key":20,"text":21,"correct":14},"C","活动历时估算内容包括确定实施项目活动必须付出的工作努力、所需的资源数量、工作时间",{"key":23,"text":24,"correct":14},"D","活动历时估算可采用三点估算法","在对活动进行时间估计时，可以选择项目队伍中最熟悉具体活动性质的个人或团体来完成估计。而活动排序过程依据活动清单、活动清单属性、项目范围说明书和里程碑清单，首先确定项目各活动之间的顺序。活动历时估算过程在活动排序过程之后进行。活动历时估算的工具、技术和方法有：专家判断、类比估算法、基于定额的历时、三点估算、预留时间、最大活动历时。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]