[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388745":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388745,172,1,"单选题","项目经理小张对自己正在做的一个项目进行成本挣值分析后，画出了如下所示的一张图，当前时间为图中的检查日期。根据该图小张分析：该项目进度 （ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","正常",false,{"key":16,"text":17,"correct":14},"B","落后",{"key":19,"text":20,"correct":21},"C","超前",true,{"key":23,"text":24,"correct":14},"D","无法判断","由该题可以看出，在当前时间，AC>EV，CV PV，SV>0，表示项目的实际进度超过预算进度，因此说明进度超前。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]