[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388743":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388743,172,1,"单选题","在下面的项目网络图中（时间单位为天），如果活动A的实际开始时间是5月1日早8时，在不延误工期的情况下，活动B最晚应在 （ ） 前结束。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5月5日早8时",false,{"key":16,"text":17,"correct":14},"B","5月6日早8时",{"key":19,"text":20,"correct":21},"C","5月7日早8时",true,{"key":23,"text":24,"correct":14},"D","5月8日早8时","如果活动A的实际开始时间是5月1日早8时，在不延误工期的情况下，活动B最晚应在5月1日+6天（活动B的最晚结束时间为6）=5月7日前结束，故选C。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]