[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388742,172,1,"单选题","关于活动资源估算正确的叙述是 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进行活动排序时需要考虑活动资源估算问题",false,{"key":16,"text":17,"correct":14},"B","活动资源估算过程与费用估算过程无关",{"key":19,"text":20,"correct":14},"C","活动资源估算的目的是确定实施项目活动所需的资源数量",{"key":22,"text":23,"correct":24},"D","企业基础设施资源信息可以用于活动资源估算",true,"活动资源估算包括决定需要何种资源和资源应该用多少，以及何时使用资源来有效地执行项目活动。活动资源估算过程利用企业环境因素包含的有关基础设施资源有无或是否可利用的信息。进行活动排序时不需要考虑活动资源估算问题，活动资源估算过程与费用估算过程相关，而活动资源估算的目的不止是确定资源数量，还包括种类，和使用时间。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]