[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388737":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388737,172,1,"单选题","项目经理向往在做软件项目成本估算时，先考虑了最不利的情况，估算出项目成本为120人日，又考虑了最有利的情况下项目成本为60人日，最后考虑一般情况下的项目成本可能为75人日，该项目最终的成本预算应为（ ）人日",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","100",false,{"key":16,"text":17,"correct":14},"B","90",{"key":19,"text":20,"correct":21},"C","80",true,{"key":23,"text":24,"correct":14},"D","75","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]