[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388736":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388736,172,1,"单选题","下图中，工作E总时差是 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":14},"C","3",{"key":22,"text":23,"correct":24},"D","4",true,"关键路径ABDF=12；E的总时差= E的最迟开始-E的最早开始=7-3=4。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]