[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388733":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388733,172,1,"单选题","以下工程进度网络图中，若结点0和6分别表示起点和终点，则关键路径为 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0→1→3→6",false,{"key":16,"text":17,"correct":14},"B","0→1→4→6",{"key":19,"text":20,"correct":21},"C","0→1→2→4→6",true,{"key":23,"text":24,"correct":14},"D","0→2→5→6","本题主要考查关键线路。所谓关键线路：① 在一条线路中，每个工作的时间之和等于工程工期，这条线路就是关键线路。② 若在一条线路中，每个工作的时差都是零，这条线路就是关键线路。根据定义我们可以求出关键线路是0→1→2→4→6，答案是C。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]