[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388732,172,1,"单选题","下图3是一个软件项目的活动图，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，活动FG的松弛时间为（2）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","19",false,{"key":16,"text":17,"correct":18},"B","20",true,{"key":20,"text":21,"correct":14},"C","21",{"key":23,"text":24,"correct":14},"D","24","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]