[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388729,172,1,"单选题","以下不具有“完成—开始”关系的两个活动是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","系统设计，设计评审",false,{"key":16,"text":17,"correct":14},"B","系统分析，需求评审",{"key":19,"text":20,"correct":21},"C","需求评审，周例会",true,{"key":23,"text":24,"correct":14},"D","确定项目范围，制订WBS","周例会是一个周期性的管理活动。它与需求评审没有固定的“完成一开始”关系。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]