[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388726":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388726,172,1,"单选题","关键路径法是利用进度计划网络图所进行的一种分析技术，下面关于关键路径的说法中正确的是 （ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","网络图中只有一条关键路径",false,{"key":16,"text":17,"correct":14},"B","关键路径上各活动的时间之和最少",{"key":19,"text":20,"correct":14},"C","非关键路径上某活动发生延误后项目总工期必然会发生延误",{"key":22,"text":23,"correct":24},"D","非关键路径上的活动延误时间如果不超过总时差，项目总工期就不会发生延误",true,"总时差表示不影响总工期的时间。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]