[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388719":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388719,172,1,"单选题","创建工作分解结构是项目范围管理的重要内容，该项活动的输出包括工作分解结构（WBS）、WBS字典、变更申请、范围管理计划（更新）和 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","范围基线",true,{"key":16,"text":17,"correct":18},"B","项目章程",false,{"key":20,"text":21,"correct":18},"C","绩效报告",{"key":23,"text":24,"correct":18},"D","工作说明书","制订工作分解结构的工作成果包括：WBS和WBS字典、范围基准和更新的项目管理计划。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]