[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388718":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388718,172,1,"单选题","项目经理在进行大项目的WBS分解时， （ ） 是错误的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按照项目的组织结构编制树形结构的WBS",false,{"key":16,"text":17,"correct":14},"B","按照项目的产品结构编制列表式的WBS",{"key":19,"text":20,"correct":14},"C","按照项目的生命周期编制鱼刺图式WBS",{"key":22,"text":23,"correct":24},"D","按照项目风险分解结构编制树形结构的WBS",true,"树形WBS适合中小项目，不适合大项目。因为树形结构指的是数据元素之间存在着“一对多”的树形关系的数据结构，是一类重要的非线性数据结构，因此不适合于大型项目项目风险分解。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]