[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388704,172,1,"单选题","（ ）是用来显示分配给每个工作包的项目资源的表格。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","WBS",false,{"key":16,"text":17,"correct":14},"B","OBS",{"key":19,"text":20,"correct":14},"C","RBS",{"key":22,"text":23,"correct":24},"D","RAM",true,"RAM（责任分配矩阵）是用来显示分配给每个工作包的项目资源的表格。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]