[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388690":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388690,172,1,"单选题","项目范围变更控制，包括 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","一系列正规的证明文件，用于定义正规项目文件的变更步骤",false,{"key":16,"text":17,"correct":14},"B","一系列文档程序，用于实施技术和管理的指导和监督，以确定和记录项目条款的功能和物理特征、记录和报告变更、控制变更、审核条款和系统，由此来检验其与要求的一致性",{"key":19,"text":20,"correct":21},"C","审批项目范围变更的一系列过程，包括书面文件、跟踪系统和授权变更所必须的批准级别",true,{"key":23,"text":24,"correct":14},"D","用于项目需求获取的一些措施，如果没有执行这些措施就不能被变更","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]