[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388684":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388684,172,1,"单选题","下面属于项目范围控制活动的是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对项目的绩效情况进行分析，确定是否偏离设定的范围基准",true,{"key":16,"text":17,"correct":18},"B","对详细的范围说明书进行评审，提交客户签字确认",false,{"key":20,"text":21,"correct":18},"C","与客户充分沟通以获取项目的详细需求",{"key":23,"text":24,"correct":18},"D","与客户开展审查或检查活动，判断工作和交付成果是否符合设定的标准","范围控制是监控项目状态如项目的工作范围状态和产品范围状态的过程，确保所有请求的变更和推荐的纠正行动，都要通过整体变更控制过程处理。当变更发生并且集成到其他控制过程时，项目范围控制也被用来管理实际的变更。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]