[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388672":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388672,172,1,"单选题","某公司中标一个企业信息化系统开发项目，合同中该项目包括：人事系统、OA系统和生产系统。下图为项目经理制作的WBS，此处项目经理违反了关于WBS的 （ ） 原则。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","WBS需要考虑将不同的人员的工作分开",false,{"key":16,"text":17,"correct":14},"B","WBS中各项工作是为提供可交付成果服务的",{"key":19,"text":20,"correct":14},"C","可以按照系统子系统来逐层分解 WBS",{"key":22,"text":23,"correct":24},"D","一个工作单元只能从属于某个上层单元",true,"\"OA系统\"与\"人事系统下面都有\"\"员工培训\"，这违反了WBS划分原则的\"一个工作单元只能从属于某个上层单元\"的原则。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]